Case 99: Should a factory buy a welding robot?
A metal works weighs a full robot cell, a smaller collaborative robot or staying manual. Compare payback, net present value and the volume needed.
Automation is easy to admire and hard to evaluate. A robot never takes a day off, never tires and welds the same seam the same way every time. It also costs a great deal at the start, needs programming and maintenance and does nothing if the factory has no work for it. The question for the owner of a metal works is not whether robots are good, but whether this robot, on this line, with this volume of work, will earn back what it costs. The answer depends on a handful of numbers: what the robot replaces, what it costs to run, how much waste it saves and, above all, how busy it will be. In this case you play the operations head of a metal works considering a welding robot. You will practise computing the yearly saving from a machine, finding the payback and the net present value of an investment, testing the result against a fall in volume and a cost overrun, and comparing a large cell with a smaller, cheaper one.
This is a composite case. Fabrico, its people and its figures are invented for teaching, built on patterns common among fabrication shops that consider automation. No real company is described, and no number here should be quoted as a fact about any real firm.
The decision
Deepak Rao, operations head at Fabrico, a metal works that makes frames and enclosures, has a proposal from an equipment supplier. A robotic welding cell would take over the work of the welding bay, where 12 operators, six on each of two shifts, weld parts for about ₹30 crore of output a year. The supplier shows him a cell that can run both shifts with one technician to look after it. The owner is attracted by the saving. The union representative asks what will happen to the 12 welders. The finance head asks for a payback and a worst case. Deepak has the figures and a second, smaller option.
Background
The welding bay today. Twelve operators cost about ₹5.0 lakh each a year, fully loaded with wages, benefits and overtime: ₹60 lakh in all. Wages rise about 8 per cent a year. Scrap and rework, from welds that fail inspection, cost about 3 per cent of output.
Option A: stay manual. No investment.
Option B: a full robotic welding cell.
Costs ₹2.4 crore, including the robots, fixtures, safety fencing, integration and training.
Replaces all 12 operators in the bay.
Needs one technician, costing ₹7 lakh a year.
Maintenance and spares cost about 8 per cent of the price, ₹19.2 lakh a year.
Halves scrap and rework, from 3 to 1.5 per cent of output, which saves about ₹31.5 lakh a year.
Lasts 8 years, with no resale value.
Option C: a smaller collaborative robot cell.
Costs ₹1.1 crore.
Replaces 5 operators, who work alongside it on the simpler parts.
Needs no extra technician, and maintenance is about 8 per cent of the price, ₹8.8 lakh a year.
Saves about ₹12 lakh a year in scrap and rework.
Lasts 8 years.
The cost of money. Fabrico uses 12 per cent a year to compare cash received later with cash spent now.
The numbers
Exhibit 1: the yearly saving
For option B, in the first year:
· ₹ lakh a yearWages saved: 12 operators × ₹5.0 lakh · +60.0
Scrap and rework saved · +31.5
Maintenance and spares · −19.2
Technician · −7.0
Net saving in year 1 · +65.3
The net saving is ₹65.3 lakh a year at today's wages. The simple payback, the cost divided by the yearly saving, is ₹240 lakh ÷ ₹65.3 lakh = 3.7 years. With wages rising 8 per cent a year, the wage saving grows, and cumulative cash turns positive in the fourth year.
End of year · Cumulative cash, option B1 · −₹174.7 lakh
2 · −₹104.6 lakh
3 · −₹29.3 lakh
4 · +₹51.6 lakh
5 · +₹138.5 lakh
8 · +₹440.6 lakh
For option C, the first-year saving is ₹25 lakh of wages and ₹12 lakh of scrap, less ₹8.8 lakh of maintenance, ₹28.2 lakh, and the simple payback is ₹110 lakh ÷ ₹28.2 lakh = 3.9 years.
Exhibit 2: the net present value
Payback ignores what happens after the money is recovered and treats a rupee in year 5 as equal to a rupee today. The net present value (NPV) adds the savings over the machine's life at their value today, and subtracts the cost.
· A. Stay manual · B. Full robot cell · C. Collaborative robotInvestment · none · ₹240 lakh · ₹110 lakh
Net saving, year 1 · none · ₹65.3 lakh · ₹28.2 lakh
Simple payback · not applicable · 3.7 years · 3.9 years
NPV over 8 years at 12% · ₹0 · +₹165.0 lakh · +₹63.7 lakh
NPV per ₹100 invested · not applicable · ₹69 · ₹58
Both machines pay: NPV is positive. The full cell is worth more in total, ₹165.0 lakh against ₹63.7 lakh, and earns more per rupee invested. Its advantage comes from replacing more people and cutting more scrap, and the price of the extra capacity is a larger commitment.
Exhibit 3: how much work the robot needs
Almost all of the saving depends on the robot being fully used. Wages are saved only if the work is there: if the bay has less to weld, the operators who would have been needed are fewer, and the saving is smaller, while the maintenance and technician costs stay the same. The table shows NPV for different levels of volume, as a share of the volume Fabrico expects.
Volume as a share of plan · B. Full robot cell · C. Collaborative robot100% · +₹165.0 lakh · +₹63.7 lakh
80% · +₹58.0 lakh · +₹20.2 lakh
70% · +₹4.4 lakh · −₹1.5 lakh
60% · −₹49.1 lakh · −₹23.3 lakh
50% · −₹102.6 lakh · −₹45.0 lakh
The full cell breaks even at 69 per cent of planned volume, and the smaller one at 70.5 per cent. A fall of 30 per cent in work is enough to wipe out the whole gain. Below that, each 10 points of volume lost costs about ₹53 lakh for the full cell. The risk of the investment is concentrated in one number, the volume of welding Fabrico will actually have.
Exhibit 4: other risks
Volume is not the only number that could be wrong. The table shows NPV for the full cell as other assumptions change.
Change · NPV of the full cellBase case · +₹165.0 lakh
Wages rise 4% a year, not 8% · +₹121.8 lakh
Wages do not rise · +₹84.4 lakh
Scrap saving is half the estimate (₹15 lakh) · +₹83.0 lakh
No scrap saving · +₹8.5 lakh
Cost of the cell is 25% higher · +₹81.1 lakh
Cost of the cell is 50% higher · −₹2.7 lakh
The cell is exposed to three risks. If wages grow more slowly, the saving falls: with no wage growth NPV is ₹84.4 lakh. If the scrap saving does not come, because the products are too varied or the programming is imperfect, NPV falls to ₹8.5 lakh, a lot of the value. And a cost overrun of 50 per cent, common in automation projects because of integration and safety work, would make the investment about break-even.
Questions to consider
1. Why is simple payback a useful first test but not enough on its own?
2. Why does the volume of work matter so much to the investment?
3. Which risk in Exhibit 4 is most worrying, and what could Deepak do to reduce it?
4. Why might the smaller cell be the better choice even though its NPV is lower?
5. What would you do for the 12 welders, and how does this affect the case?
6. What would you recommend, and what would you want to see before signing?
Analysis
Step 1: what the robot actually saves
The saving has three parts. The biggest is wages: ₹60 lakh a year, and growing, since wages rise 8 per cent a year while the robot's cost does not. The second is quality: welds are more consistent, and scrap and rework fall by half, worth ₹31.5 lakh. The third is a negative: maintenance, ₹19.2 lakh, and the technician, ₹7 lakh. The robot is not free to run. It replaces most of the labour cost but leaves a cost of about 44 per cent of the wages it replaces.
It is useful to think of what a robot does not change. It does not change the amount of steel, the time of the crane or the design of the parts. It changes one kind of cost, at the welding station. A robot makes sense when that cost is a large share of the total and when the work is repetitive enough for a machine to do. A factory that makes many different one-off parts will find a robot slow to reprogram and often idle, and a bay that makes the same frame in thousands is its ideal.
Step 2: payback and its limits
A payback of 3.7 years on an 8-year machine is reasonable, and many firms look for under four years. But payback has two flaws. It ignores everything after the money is recovered, and it ignores the timing of cash within the payback period. A machine with a 3.7-year payback and a six-year life is a much better investment than one with the same payback and a four-year life, but payback cannot tell them apart.
NPV fixes both. It counts all the years, and values later savings at less than early ones. It gives a single figure, ₹165.0 lakh, that can be compared across projects. A positive NPV means the investment earns more than the 12 per cent that Fabrico demands of its money. NPV, in turn, depends on the assumptions behind it, and a precise figure should not hide how uncertain the inputs are.
Step 3: volume is the key risk
The robot cell costs ₹240 lakh whatever the volume, and its maintenance and technician cost ₹26.2 lakh a year whatever the volume. Only the savings change with volume. If the bay has 70 per cent of the planned work, the savings fall to 70 per cent of their value and the fixed costs do not fall, and NPV falls to ₹4.4 lakh, almost nothing. At 60 per cent, it is a loss of ₹49 lakh.
A fall of 30 per cent in welding work is not a remote event. It can come from the loss of a customer, a change in the product mix, a downturn or a design change that removes welds. Deepak should ask three questions. How firm is the volume? Is it spread over many customers or concentrated in one? And what else could the cell do if its main work went away? A cell that can be re-tooled for other products has a safety net. One that is built for a single part does not.
Step 4: why the smaller cell might be better
The collaborative robot has a lower NPV, ₹63.7 lakh, but it also has a lower commitment, ₹110 lakh, and a break-even volume that is about the same, 70.5 per cent. If the volume is 100 per cent of plan, it earns ₹58 per ₹100 invested against ₹69 for the full cell. The case for it rests on other qualities.
Flexibility. A collaborative robot is moved, reprogrammed and used on different jobs more easily, and it works beside people, so the plant can use it where it is needed.
Risk. A smaller sum is at stake. A 50 per cent cost overrun on option C would cost ₹55 lakh, on option B ₹120 lakh.
People. Replacing 5 workers, not 12, is easier to manage, and some of them can be moved to other work.
Learning. A first, smaller project teaches the plant how to program, maintain and schedule a robot, and prepares it for a larger investment later.
A staged approach, starting with the collaborative robot and adding the larger cell when volume and skills are proven, may be worth more than the choice between the two.
Step 5: the people
The 12 welders are not a detail. They are the reason the saving exists, and they are also colleagues, with skills and families, in a plant that depends on their goodwill. How Fabrico treats them affects whether the project works.
A reasonable approach has several parts. Be open early: tell the workforce what is planned and why, before rumours do. Redeploy where possible: welders know the product and can be trained for inspection, programming, fixture design and other roles, and some can become the robot's operators. Use natural attrition: if the plant has several retirements and resignations each year, the headcount can fall without dismissals, over a period. For those who cannot be placed, offer retraining and a fair severance, following the law and any agreements.
These steps have a cost, and it should be in the case. If Fabrico redeploys half the welders to jobs it would otherwise have filled from outside, the saving from them is real, since it avoids hiring. If it pays severance of six months for four people, that is ₹10 lakh of one-off cost. These amounts are small compared with the NPV, but a plant that handles the change badly may lose its experience, its goodwill and its output, which are worth far more.
Step 6: what to check before signing
Before the board commits ₹2.4 crore, Deepak should do the following.
Test the volume. Look at orders for the last three years, by customer and by part, and at the pipeline for the next two. Decide what share of the welding is stable enough for a robot.
Test the savings. Have the supplier weld a sample of Fabrico's actual parts, and measure the cycle time, the quality and the reprogramming time for new parts.
Get the full cost. Ask for a fixed-price quote including fixtures, safety and training, and a margin for overrun.
Check the supplier. Visit plants that use the same cell, and ask about uptime, support and surprises.
Define the plan for the people. And the date by which the first results will be reviewed.
Step 7: the recommendation
Deepak might say: "Start with the collaborative robot cell, and prepare for the larger one. On our figures, the full cell earns ₹165 lakh of net present value over eight years against ₹64 lakh for the collaborative cell, but it breaks even only if we keep 69 per cent of the planned welding volume, and a cost overrun of 50 per cent would wipe out its gain. The smaller cell costs ₹110 lakh, pays back in 3.9 years and breaks even at 70 per cent of volume, so we risk less while we learn. Check the volume by customer first, weld a trial batch of our own parts, get a fixed-price quote with a margin for overrun and agree a plan with the workforce that uses redeployment and natural attrition. Review after twelve months, and move to the full cell if volume has held and the saving matches the plan."
What happened
This part of the case is an illustrative epilogue, not a real outcome.
Fabrico installed the collaborative cell. A trial batch showed that about 40 per cent of the parts could be welded by the robot without reprogramming problems, and the cell replaced five operators' work on those parts. Three of the five were redeployed to inspection and fixture work, and two left through retirement and a voluntary exit scheme. Scrap fell by about a third on the parts the robot handled. After twelve months the net saving was ₹26 lakh, close to the ₹28.2 lakh planned. Volume held at 96 per cent of plan, and Deepak asked the board for a second cell the following year, with a larger fenced cell for the high-volume frames.
Key takeaways
A robot cell replaces most of a labour cost but leaves a cost of maintenance and a technician. The full cell saved ₹65.3 lakh in year 1 on a cost of ₹240 lakh, a payback of 3.7 years.
Simple payback ignores the life of the machine and the timing of cash. Net present value counts both. The full cell was worth +₹165.0 lakh over eight years at 12 per cent and the collaborative cell +₹63.7 lakh.
Volume is the key risk. Fixed costs stay when work falls: the full cell broke even at 69 per cent of planned volume and lost ₹49 lakh at 60 per cent.
Other risks mattered: with no scrap saving NPV fell to ₹8.5 lakh, and a 50 per cent cost overrun made the project about break-even.
A smaller, flexible cell commits less money, teaches the plant and can be a first step. Judge it on risk and learning, not only NPV.
Plan for the people from the start: be open, redeploy, use attrition and offer fair terms. Check volume, savings and cost before signing.
Try this
Evaluate an automation or equipment investment of your own. Set aside forty-five minutes.
1. Choose a machine or system that would replace work now done by people or older equipment. Write the cost, the number of people or hours replaced, the yearly cost of each, wage growth, maintenance and extra staff, the quality saving and the life of the machine.
2. Compute the saving in year 1, the simple payback and the net present value at a cost of money you choose.
3. Test the volume at 80, 70 and 60 per cent of plan, and find the break-even volume.
4. Test a cost overrun of 25 and 50 per cent, no quality saving and slower wage growth.
5. Design a smaller or staged version and compare its risk and NPV.
6. Write a five-sentence recommendation: the choice, the numbers, the break-even volume, the checks you would do before signing and what you would do for the people affected.
A good result is a first-year saving, a payback and an NPV, a break-even volume, tests of the main risks, a smaller or staged alternative and a plan for the people affected. This is the last of the e-commerce and manufacturing cases in this set.
Tags: Case study Manufacturing Automation Capital investment Payback