Case 94: Make or buy a component for a car-parts maker
A car-parts maker weighs buying a component, making it or signing a volume contract. Compare yearly cost by volume, the break-even volume and supply risk.
Every manufacturer faces the same question about each part of its product: should it make the part itself, or buy it from someone else? Buying is simple. The supplier takes the machine, the staff and the risk, and the manufacturer pays a price per unit. Making needs a machine, people and space, and so it brings fixed costs that do not go away if volumes fall. But a part made in-house costs less per unit to produce, because there is no supplier's profit in the price. The answer therefore depends on volume: at low volumes, the fixed costs of making are spread over too few units, and at high volumes they are spread thinly enough that making wins. In this case you play the finance head at a car-parts maker deciding whether to make a component it has always bought. You will practise comparing yearly cost at different volumes, finding the volume at which making breaks even, adding the cost of supply risk, and testing the answer against the price and machine cost you are least sure of.
This is a composite case. Gearwell, its people and its figures are invented for teaching, built on patterns common among component and equipment makers. No real company is described, and no number here should be quoted as a fact about any real firm.
The decision
Sunil Verma, finance head at Gearwell, which makes gearboxes for small commercial vehicles, reviews the bill of materials of a new gearbox and sees that a machined housing is the single biggest bought-in part. Gearwell buys it from a supplier at ₹420 a unit. The plant manager says Gearwell could make it in-house on a new machine and save money. The purchase head says the supplier is reliable and the volume is uncertain. Sunil has to compare the options on cost and risk before the board meets.
Background
Buying. The supplier charges ₹420 a unit. There is no fixed cost, and the price does not change with volume.
Making.
The machine costs ₹6 crore and lasts 7 years. Gearwell values money at 12 per cent a year, so the machine costs about ₹1.32 crore a year when its price is spread over its life with interest (₹6 crore × 0.2191).
Other fixed costs, such as supervision, maintenance and floor space, are ₹1.1 crore a year.
The fixed cost of making is therefore ₹2.42 crore a year, whatever the volume.
Material, labour and power cost ₹290 per unit.
So making saves ₹130 on every unit (₹420 − ₹290) and costs ₹2.42 crore a year to be able to.
A volume contract. The supplier offers a lower price of ₹395 a unit if Gearwell commits to buy at least 150,000 units a year. Below that volume, Gearwell pays for 150,000 units anyway. This is called a take-or-pay contract.
Volumes. The gearbox is new. Gearwell's sales team expects 120,000 units next year, 200,000 in a good year and 280,000 in a very good one, but no one is sure. Sunil gives them weights of 25, 50 and 25 per cent.
The numbers
Exhibit 1: yearly cost by volume
All figures are in crore of rupees a year.
Volume a year · A. Buy at ₹420 · B. Make in-house · C. Buy under the volume contract · Cheapest80,000 · 3.36 · 4.73 · 5.92 · Buy
120,000 · 5.04 · 5.89 · 5.92 · Buy
160,000 · 6.72 · 7.05 · 6.32 · Contract
200,000 · 8.40 · 8.21 · 7.90 · Contract
300,000 · 12.60 · 11.11 · 11.85 · Make
At 80,000 units, making costs ₹1.37 crore more than buying, since the fixed cost of ₹2.42 crore is spread over so few. At 300,000, making costs ₹1.49 crore less. The contract is cheapest in the middle range, at 160,000 to 200,000, but is the worst at low volumes, because Gearwell pays for 150,000 units whether or not it needs them: at 80,000 it costs ₹5.92 crore against ₹3.36 crore for simply buying.
Exhibit 2: the break-even volume
Making and buying cost the same when the fixed cost is exactly covered by the saving on each unit: ₹2.42 crore ÷ ₹130 = 185,700 units a year. Below that, buy. Above it, make.
The break-even is a single number that the plant manager and the purchase head can argue about. The plant manager believes that volume will exceed it. The purchase head believes it might not. Sunil's task is to show how much each assumption moves it.
Change · Break-even volumeBase case · 185,700
Supplier price ₹380 · 268,300
Supplier price ₹460 · 142,000
Machine costs ₹5 crore · 168,900
Machine costs ₹8 crore · 219,500
In-house cost ₹260 a unit · 150,900
In-house cost ₹330 a unit · 268,300
The result is sensitive to the supplier's price and to Gearwell's own unit cost. A ₹40 fall in the supplier's price lifts the break-even from 185,700 to 268,300, 44 per cent. A ₹40 rise in Gearwell's own cost has the same effect. Sunil should test both numbers hard: ask the supplier what it would do on price at 200,000 units a year, and ask the plant manager for the evidence behind ₹290.
Exhibit 3: supply risk
Cost is not the only difference. When Gearwell buys, it depends on a supplier. A strike, a fire or a quarrel at the supplier would stop production of the gearbox. Sunil estimates that there is an 8 per cent chance a year of a disruption that would cost Gearwell about ₹3 crore in lost production, an expected cost of ₹0.24 crore a year. When Gearwell makes, there is a 3 per cent chance a year of a machine breakdown costing about ₹2 crore, an expected cost of ₹0.06 crore. Making is therefore ₹0.18 crore a year safer.
Adding the risk shifts the break-even volume down to about 171,900 units, a fall of 13,800. At 200,000 units, making saves ₹0.37 crore a year against buying once risk is counted, not ₹0.19 crore.
Exhibit 4: averaging over uncertain volume
The plan does not know the volume. Weighting 120,000, 200,000 and 280,000 units by 25, 50 and 25 per cent, the expected yearly saving from making instead of buying is:
0.25 × (−₹0.86 crore) + 0.50 × (+₹0.19 crore) + 0.25 × (+₹1.23 crore) = +₹0.19 crore a year.
On average, making saves about ₹0.19 crore a year, 2 per cent of the cost of buying. That is small compared with the swings in the table: at 120,000 units making costs ₹0.86 crore more, and at 280,000 it saves ₹1.23 crore. The decision is close to a coin toss on average. What the figures cannot show is what each option does to Gearwell's freedom to change.
Questions to consider
1. Why does making only pay above a certain volume, and what sets that volume?
2. Which of the three options is cheapest at 120,000, 200,000 and 300,000 units, and why?
3. Which assumption in Exhibit 2 could change the answer most, and how could Sunil test it?
4. How does supply risk change the case, and what else besides cost matters to the choice?
5. What does it mean that the expected saving from making is small, and what would you do about uncertainty on volume?
6. What would you recommend, and what would you say to the supplier?
Analysis
Step 1: fixed cost and variable cost
The whole case rests on the difference between two kinds of cost. When Gearwell buys, every cost is variable: it pays ₹420 for each unit, and pays nothing if it needs none. When Gearwell makes, part of the cost is fixed: the machine, supervision and space cost ₹2.42 crore a year whether it makes 20,000 units or 200,000. Only the material, labour and power, ₹290 a unit, are variable.
The consequence is that making has a high fixed cost and a low variable cost, and buying has none of the first and a high version of the second. The two lines in the chart cross at one volume. A manufacturer with high volume gains from making, because it spreads the fixed cost thinly. One with low or unsure volume gains from buying, because it pays only for what it uses. The break-even of about 186,000 units is where the saving of ₹130 a unit exactly pays for the fixed cost.
Step 2: how sure is the volume
The gearbox is a new product, and the volume is a forecast. If Gearwell sells 120,000 units, making costs ₹0.86 crore a year more than buying. If it sells 280,000, it saves ₹1.23 crore. The difference between the two outcomes is ₹2.1 crore, and Gearwell does not know which it will get.
A decision that depends on a forecast should be tested against the forecast being wrong. In this case, the average saving, ₹0.19 crore, hides a wide spread. For a company that can absorb a poor year, a bet on making has a good chance of paying. For one that is short of capital, committing ₹6 crore to a machine for a product that may not sell is a heavy risk. The machine is also hard to sell if the product fails: a machine bought for ₹6 crore may fetch far less second-hand.
Step 3: the middle way
The contract in option C is a way of getting part of the saving without the machine. At ₹395, it cuts ₹25 off every unit, and in the volume range of 160,000 to 200,000 it is the cheapest option. It has a different risk: the take-or-pay clause. If volume falls to 80,000, Gearwell pays for 150,000 and wastes ₹2.6 crore.
A contract can also be written in other ways, and Sunil should negotiate them.
A lower minimum. A commitment of 100,000 units, not 150,000, with a smaller discount.
Tiered prices. ₹420 up to 100,000, ₹400 up to 200,000 and ₹385 above that. The price falls as volume rises, without a promise to buy any minimum.
A shorter term. A two-year contract that can be renewed once the volume is known.
Shared tooling. The supplier pays for the machine and recovers the cost in the price, with a buy-out clause.
With a good contract, Gearwell can wait: buy for the first two years, learn the real volume and then decide whether to make.
Step 4: what cost does not capture
Several factors beyond cost matter and are hard to put in a table.
Quality and control. A machined housing is a critical part. Making it in-house gives Gearwell control of tolerances and of the speed at which it can change the design. Buying it means depending on the supplier's quality system.
Know-how. A supplier may have skills Gearwell lacks, such as casting or heat treatment. If the plant manager's cost of ₹290 assumes a level of skill that Gearwell has not reached, it is optimistic.
Capacity and attention. A new machine needs people, a place and management time. A plant that is already stretched may not do it well.
Strategy. Is the housing a part where Gearwell wants to be good, because it is a source of advantage, or is it a commodity? A firm should usually make what is core to its product and buy what is not.
Supplier relationship. A supplier that has a large share of Gearwell's business can be a partner, and one that is threatened by a make decision may withdraw its cooperation.
Step 5: how to learn more cheaply
The cost of being wrong on a ₹6 crore machine justifies spending a little to learn before deciding. Sunil can take several steps.
Get a firm quote from the supplier at several volumes, and ask for a second supplier's quote.
Test the in-house cost by asking the plant manager to build a bottom-up estimate of material, labour and power, and compare it with the costs of a similar part Gearwell already makes.
Start with a smaller or used machine, or a lease that can be ended, to reduce the fixed cost and the risk.
Make a small batch on existing equipment to measure real costs and quality before committing.
Stage the decision. Buy in year 1, with the option to make from year 2 if volume exceeds 160,000.
Step 6: the cost of changing your mind
A decision to make a part is hard to undo. If volume disappoints, Gearwell is left with a machine that may fetch only a third of its price, and a team that has to be redeployed. A decision to buy is easier to reverse, but not free: the supplier may have used its capacity for other customers by the time Gearwell wants to start making, and its price may rise once it knows Gearwell has no alternative.
Sunil can put a number on this. If the machine could be resold for ₹2 crore after three years, the loss from a wrong decision to make is about ₹4 crore less the savings made in the meantime, which is large against a possible saving of ₹0.2 crore a year. A decision to buy under a contract with no minimum can be reversed at almost no cost. That asymmetry is a reason to prefer buying while the volume is unknown, and to make only when the volume has been proven. It is the logic of keeping an option open: when a choice is close, the one that is cheaper to undo is the better one.
### Step 7: the recommendation
Sunil might say: "Buy for the first year, under a contract with no minimum and prices that fall with volume, and decide on the machine when we know the real volume. Making breaks even at about 186,000 units a year, or about 172,000 after counting the lower risk of supply disruption, and our expected volume is on that line: making saves ₹0.19 crore a year on average, but costs ₹0.86 crore more than buying if we sell only 120,000 units. The take-or-pay contract at ₹395 is cheaper at 160,000 to 200,000 units but would waste ₹2.6 crore at 80,000. Ask the supplier for tiered prices and test the plant's cost of ₹290 against a trial batch. If volume passes 200,000 in the first year, order the machine."
What happened
This part of the case is an illustrative epilogue, not a real outcome.
Gearwell negotiated a tiered price with the supplier: ₹420 up to 100,000 units, ₹402 to 200,000 and ₹390 above that, with no minimum. In the first year it sold 148,000 gearboxes, below the 200,000 hoped for but above the 120,000 low case. A trial batch on existing equipment showed an in-house cost of ₹318 a unit, not ₹290, because of scrap on the first runs, which moved the break-even to about 237,000 units. In the second year volume rose to 196,000. Sunil reported that buying under the tiered price had cost about ₹1.0 crore less than making would have in the first year and ₹0.6 crore less in the second, and that the board had deferred the machine.
Key takeaways
Making has a fixed cost and a low variable cost, and buying has no fixed cost and a higher price. The two cross at one volume.
Making cost ₹2.42 crore a year in fixed costs and saved ₹130 a unit, so it broke even at about 186,000 units. Below that, buying was cheaper.
The break-even moved a great deal with the supplier's price (142,000 to 268,000 units for a ₹40 change either way) and Gearwell's own unit cost.
Counting supply risk lowered the break-even to about 172,000 units, since a bought part carried an 8 per cent chance of a ₹3 crore disruption against 3 per cent and ₹2 crore for a made one.
With uncertain volume, the expected saving from making was only ₹0.19 crore a year, with outcomes from −₹0.86 crore to +₹1.23 crore. A take-or-pay contract was cheapest in the middle range and the worst at low volume.
Negotiate flexible contracts, test the in-house cost with a trial, and stage the decision so that you learn the volume before committing to a machine.
Try this
Decide whether to make or buy a part of your own. Set aside forty-five minutes.
1. Choose a component you currently buy. Write the supplier's price, the cost of the machine and its life, the cost of capital, the other fixed costs of making and the variable cost per unit.
2. Compute the yearly cost of making and of buying at five volumes, and the break-even volume.
3. Add the chance and cost of a supply disruption for buying and of a breakdown for making, and see how the break-even moves.
4. Test the supplier's price, your own variable cost and the cost of the machine up and down by a fifth.
5. Design a contract or a staged plan that reduces the cost of being wrong about volume.
6. Write a five-sentence recommendation: the choice, the numbers, the break-even volume, the assumption that matters most and the step you would take first.
A good result is a cost table at five volumes for buying, making and a contract, a break-even volume, a sensitivity test, an allowance for supply risk and a staged plan. Case 95 looks at a daily decision on the factory floor: how many units to make before changing the machine over.