Case 65: How to handle a seasonal demand peak
A teaching case on a sweets maker facing a festive peak: overtime, subcontracting or a permanent line? Find the cheapest way as the season length changes.
Some businesses spend most of the year at one level and a few weeks at another. A sweets maker in the festive season, a retailer around a sale, a tax adviser in March and an e-commerce warehouse in October all face a peak that is much higher than the rest of the year. A company that builds capacity for the peak has idle capacity for months. A company that builds for the normal level loses sales when the peak comes. In between, there are options that cost more per unit but are paid for only when used: overtime, temporary workers, subcontracting. This case asks which mix of these is cheapest for a particular peak and how the answer changes with the length of the season and how sure the company is about the demand. It is the same problem as Case 63's warehouse peak, seen from the factory floor. You will practise comparing options with different fixed and variable costs, finding the season length at which a permanent investment pays, building a mix and testing it against uncertain demand.
This is a composite case. Meetha Kitchens, its people and its figures are invented for teaching, built on patterns common among Indian food makers. No real company is described, and the costs are illustrative.
The decision
Farida Khan, operations head of Meetha Kitchens, a maker of packaged sweets, is planning for the festive season. In most of the year the plant makes 100 units (batches) a day and sells all of them. For the 90 days of the festive season, orders reach 160 units a day, but the plant can make only 100. Farida has four ways to respond, and the owner wants to know which is best. She also knows the season is not guaranteed: it was 90 days last year but 60 the year before, and a new competitor could cut the demand.
Background
Economics. Each unit sold earns a contribution of ₹500 before any special cost of making it. The plant works 300 days a year.
The four options for the extra 60 units a day.
1. Do nothing. Sell only 100 a day and lose the extra 60.
2. Overtime. Existing workers can make up to 20 extra units a day at an extra cost of ₹200 a unit (premium pay and fatigue). A unit made on overtime therefore earns ₹300.
3. Subcontract. An outside maker can produce up to the full extra 60 units a day at an extra cost of ₹350 a unit (its margin, transport and quality checks), so each earns ₹150.
4. Add a permanent line. A new line that can make 60 extra units a day costs ₹20 lakh a year (rent, depreciation, maintenance and a minimum crew) whether or not it is used. Units it makes earn the full ₹500.
A mix is possible, for example overtime for the first 20 units and subcontracting for the other 40.
The numbers
Exhibit 1: the cost of each option over a 90-day season
The extra demand is 60 units a day for 90 days, which is 5,400 units.
Option · Units captured · Contribution per unit · Fixed cost · Net gainDo nothing · 0 · · · ₹0 (₹27.0 lakh of contribution is lost)
Overtime only · 1,800 (20 a day) · ₹300 · none · ₹5.4 lakh
Subcontract only · 5,400 · ₹150 · none · ₹8.1 lakh
Overtime plus subcontract · 1,800 + 3,600 · ₹300 and ₹150 · none · ₹10.8 lakh
Permanent line · 5,400 · ₹500 · ₹20 lakh · ₹7.0 lakh
The best choice for a 90-day season is the mix of overtime and subcontracting, at ₹10.8 lakh. It uses the cheapest flexible capacity first (overtime, at ₹200 extra) and the next cheapest (subcontracting, at ₹350) for the rest. The permanent line earns ₹27.0 lakh of contribution but costs ₹20 lakh, for a net ₹7.0 lakh.
Exhibit 2: how the best option depends on the length of the season
The flexible options earn a fixed amount per day of peak: the mix earns 20 × ₹300 + 40 × ₹150 = ₹12,000 a day. The permanent line earns 60 × ₹500 = ₹30,000 a day but has a fixed cost of ₹20 lakh a year. The longer the season, the more the permanent line's higher margin pays.
Season length · Overtime · Subcontract · Mix · Permanent line45 days · ₹2.7 lakh · ₹4.0 lakh · ₹5.4 lakh · −₹6.5 lakh
90 days · ₹5.4 lakh · ₹8.1 lakh · ₹10.8 lakh · ₹7.0 lakh
150 days · ₹9.0 lakh · ₹13.5 lakh · ₹18.0 lakh · ₹25.0 lakh
200 days · ₹12.0 lakh · ₹18.0 lakh · ₹24.0 lakh · ₹40.0 lakh
The two cross at a season of about 111 days: 18,000 extra a day for the permanent line over the mix (₹30,000 − ₹12,000) must cover ₹20 lakh, so the break-even is ₹20,00,000 ÷ ₹18,000 = 111 days. Meetha Kitchens' season is 90 days, so it is just below the break-even.
Exhibit 3: what if the peak is smaller than expected?
The peak of 160 units a day is a forecast. If demand turns out to be only 130 a day (an extra 30), for 90 days:
Option · Net gainOvertime (20 a day) plus subcontract (10 a day) · 20 × 90 × ₹300 + 10 × 90 × ₹150 = ₹6.75 lakh
Permanent line (30 a day used) · 30 × 90 × ₹500 − ₹20 lakh = −₹6.5 lakh
The permanent line loses money, because its fixed cost is paid whether the demand comes or not. The flexible mix still earns a profit. This is the main advantage of flexible capacity: you pay only when the demand comes.
Questions to consider
1. Why is the mix of overtime and subcontracting better than either alone? In what order should the flexible options be used?
2. At what season length does the permanent line become better than the flexible mix? Where does a 90-day season sit?
3. What happens to each option if the peak is smaller than forecast? Which has the more risk?
4. What things beside cost matter: quality, reliability, workers, customers and the relationship with a subcontractor?
5. How could Meetha Kitchens find out whether the season is getting longer or shorter?
6. What would you recommend to Farida?
Analysis
Step 1: use the cheapest flexible source first
Each flexible source has a limit and a price. Overtime is cheapest per unit (₹200 extra) but limited to 20 units a day. Subcontracting costs more (₹350) but can supply any amount. The cheapest way to cover 60 extra units is to use overtime to its limit and subcontract the rest. This is a merit order, the same logic as in electricity grids, where the cheapest plant is used first and the dearest last.
The mix earns ₹10.8 lakh, against ₹8.1 lakh for subcontracting alone. The difference, ₹2.7 lakh, is the saving from making 20 units a day on overtime (at ₹200 extra) rather than at the subcontractor (₹350 extra): 20 × 90 × ₹150 = ₹2.7 lakh.
Step 2: the permanent line has the best margin and the most risk
A permanent line earns the full ₹500 a unit, against ₹300 and ₹150 for the flexible sources. On 5,400 units, that is ₹27.0 lakh against about ₹10.8 lakh. But the line costs ₹20 lakh a year, and in a 90-day season it earns only ₹7.0 lakh after that. The permanent line is the best option if the season is longer than 111 days, or if the line can be used in the off-season for other products.
Here the second point deserves a thought. The line costs ₹20 lakh a year but is idle for 210 days. If Meetha Kitchens can find uses for it in the off-season, such as a second product line, contract manufacturing or a pre-festive stock-build, the fixed cost is spread over more output, and the line becomes worth building. A line used for 150 days instead of 90 breaks even against the mix. This is the logic of flattening the peak.
Step 3: flexible capacity is insurance against uncertain demand
The case for flexibility is strongest when the future is uncertain. Exhibit 3 shows the key asymmetry. If demand is 30 units a day below forecast, the flexible mix still earns ₹6.75 lakh, and the permanent line loses ₹6.5 lakh. If demand is 30 units above forecast, the permanent line gains more, but the mix also benefits. The cost of the flexible options is the lower margin, which can be seen as an insurance premium against bad outcomes.
With a forecast uncertain enough to put the season between 60 and 120 days, the flexible mix is the safer choice. At 60 days the mix earns about ₹7.2 lakh and the line loses ₹2.0 lakh (60 × 60 × ₹500 − ₹20 lakh = −₹2.0 lakh). At 120 days the mix earns ₹14.4 lakh and the line ₹16.0 lakh (₹36 lakh − ₹20 lakh).
Step 3b: weigh the plans over the seasons you might get
Since the length of the season is uncertain, a single-number comparison can mislead. Farida can weigh each plan over the seasons she thinks possible. Suppose she gives a 25 per cent chance to a 60-day season, 50 per cent to 90 days and 25 per cent to 120 days. The flexible mix earns ₹7.2 lakh, ₹10.8 lakh and ₹14.4 lakh in those cases, an expected ₹10.8 lakh. The permanent line earns −₹2.0 lakh, ₹7.0 lakh and ₹16.0 lakh, an expected ₹7.0 lakh. The line has a higher upside (₹16.0 lakh against ₹14.4 lakh) but a loss in one case in four, and its expected gain is lower by ₹3.8 lakh a year. Even a more optimistic view, with the 120-day season as likely as the 90-day (25, 37.5 and 37.5 per cent), would give the line an expected ₹8.1 lakh against ₹11.3 lakh for the mix. Only if she believes the season is likely to be longer than 111 days in most years does the line win. The exercise also shows what to learn: a better forecast of the season, from pre-orders and past years, is worth real money, because it decides a ₹20 lakh commitment.
Step 4: what the numbers leave out
Quality and reliability. Subcontractors vary in quality, and sweets are a product where a bad batch damages the brand at the most important time of year. The cost of quality control and the risk of failure may be larger than the ₹350 assumes.
Workers. Overtime of 20 units a day on top of a full day has limits: fatigue, errors, accidents and the willingness of workers to do it every festive season. A mix of temporary workers and overtime may be better.
Capacity constraints elsewhere. The plant may be limited in packaging, ingredients, storage or delivery before it is limited in production.
Subcontractor availability. In the festive season every sweet maker needs extra capacity, and good subcontractors are booked early. A relationship and a deposit may be needed.
Ingredient supply and price. A peak may also raise the cost of milk, sugar and ghee, which is not in the model.
Long-term growth. If the base demand is growing, the peak plus the growth may justify a permanent line sooner.
The learning effect. A subcontractor who makes your product may become a competitor.
Step 5: ways to improve the position
Build stock before the peak. Sweets that keep for weeks can be made in the quiet season and stored, which spreads the load. This works for products with a long shelf life and is the cheapest capacity of all.
Shift demand. Early-bird pricing, pre-orders and gift packs that sell before the festival flatten the peak.
Limit the range during the peak. Making fewer product varieties lowers changeovers and raises output from the same plant.
Use temporary workers at the base wage in place of overtime at a premium.
Contract for the subcontractor in advance, with a volume commitment, to secure capacity and a lower price.
Rent equipment for the season, rather than buying it.
Step 6: the recommendation
Farida might say: "For a 90-day season, use a mix: 20 units a day on overtime, with temporary workers where possible, and 40 units a day from a subcontractor secured by a contract signed in June. This earns about ₹10.8 lakh more than doing nothing, and loses nothing if demand disappoints. Do not build the permanent line yet: it pays only above about 111 days of peak, or if we can find 60 more days of use for it in the off-season. Start building stock of the long-life lines in the quiet months to cut the peak by about 15 units a day. Review the decision each year, using the real length of the season: if the season has averaged more than 110 days over three years, or if we find off-season work for a second line, build it."
A last point is about people. Overtime and temporary work are decisions about workers, not just about machines, and a plan that looks cheap on paper can fail if the workers will not do it. Farida should speak to the shop-floor supervisors early, agree the overtime rates and rota before the season, make sure that temporary workers are trained before the peak and not during it, and check that the subcontractor's staff meet the same hygiene standards. Plans for a peak fail most often in the week of the peak, when there is no time to fix an assumption, which is why the preparation in June matters more than the arithmetic in October.
What happened
This part of the case is an illustrative epilogue, not a real outcome.
Meetha Kitchens covered the peak with overtime and a subcontractor booked in June. Stock-building of long-life sweets moved about 12 units a day of the peak into the quiet months. The season that year was 84 days, and the mix earned about ₹9 lakh. A batch from the subcontractor failed a quality check in the second week, and the company paid for an inspector at the subcontractor's site from then on. Over the next two years the season averaged 95 days. The owner chose not to build the permanent line, and instead began a pre-order campaign that moved some demand into the weeks before the peak.
Key takeaways
Cover a peak with the cheapest flexible capacity first. Overtime (₹200 extra) for 20 units a day and subcontracting (₹350 extra) for the other 40 earned ₹10.8 lakh in a 90-day season.
A permanent line has the best margin (₹500 a unit) and a fixed cost (₹20 lakh a year). It earned ₹7.0 lakh in a 90-day season and breaks even with the mix at about 111 days.
Flexible capacity is insurance. If demand was 30 units a day below forecast, the mix earned ₹6.75 lakh and the line lost ₹6.5 lakh.
Look beyond cost: quality, worker limits, other bottlenecks, subcontractor availability and growth.
Flatten the peak by building stock, shifting demand, narrowing the range and booking capacity in advance.
Review each year with the real length of the season, and set a trigger for investing in permanent capacity.
Try this
Plan for a peak in a business of your own. Set aside forty-five minutes.
1. Choose a business with a seasonal peak, or invent one. Write the normal capacity, the peak demand, the length of the season and the contribution per unit.
2. List three or four ways to cover the extra demand, with the capacity, the extra cost per unit and any fixed cost of each.
3. Compute the net gain of each option and of a mix in merit order. Use the simulator pattern.
4. Find the season length at which the permanent investment breaks even with the flexible mix.
5. Test the plan if the peak is half as large, and list two non-cost risks.
6. Write a five-sentence recommendation: the mix, the gain, the break-even, the stock or demand-shifting steps you would take and the review trigger.
A good result is a table of options by season length, a merit order, a break-even season, a stress test for a smaller peak and a list of risks that the cost model omits. Case 66 moves from the factory to a personal decision: whether to switch jobs.
Tags: Case study Capacity planning Seasonality Overtime Subcontracting