Case 96: A third shift or a new line to meet growing demand
A plant facing rising demand weighs a third shift, a new line or both in order. Compare five-year cost, lost sales and when to build the new line.
When demand grows, a factory that is already full has to find more capacity. It can make more with the machines it has, by running them for longer hours. Or it can buy more machines. The first is cheap to start and expensive to continue. Night shifts cost more in wages, and tired people and a machine that never rests make more mistakes and break down more. The second needs a large sum up front and a long wait while the line is built, but once it is running it makes each unit more cheaply. A plant manager must decide not only which to choose but when. A new line built too early sits half-empty and costs money. One built too late loses sales. In this case you play the chief operating officer of an appliance maker whose demand is rising 12 per cent a year. You will practise comparing the yearly cost of a third shift and of a new line, finding the volume at which the new line becomes the cheaper choice, adding the cost of lost sales, and building a plan that uses both in the right order.
This is a composite case. Cooltec, its people and its figures are invented for teaching, built on patterns common among plants that expand capacity as demand grows. No real company is described, and no number here should be quoted as a fact about any real firm.
The decision
Neha Bhatia, chief operating officer at Cooltec, which makes compressors for refrigerators, is looking at the order book. The plant makes 1.2 million units a year on two shifts and is full. Orders are expected to grow by 12 per cent a year, which means 1.34 million next year and 1.5 million the year after. The production head wants a new line now, so that Cooltec is never caught short. The finance head wants to run a third shift. Neha has costs for both and a spreadsheet.
Background
The plant today. Two shifts, 1.2 million units a year, with no spare capacity. Each unit earns a contribution of ₹150 before the cost of capacity: the price less material, labour and power on a normal shift.
Option 1: a third shift on the existing line.
Adds 0.6 million units a year of capacity, taking the plant to 1.8 million.
A fixed cost of ₹1.2 crore a year for supervision, security, transport and a canteen at night.
An extra ₹45 on every unit made on the third shift: a night premium on wages (₹15), overtime, fatigue and defects (₹12), and extra maintenance and energy (₹18).
Can start within three months.
Option 2: a new production line.
Costs ₹24 crore and lasts 10 years. At Cooltec's 12 per cent cost of money, that is about ₹4.25 crore a year.
A fixed cost of ₹1.5 crore a year for the staff, maintenance and space the line needs.
The yearly cost is ₹5.75 crore, whatever the volume.
Adds 1.0 million units of capacity, taking the plant to 2.2 million, with no extra cost per unit.
Takes 18 months to build and bring into production.
Three plans.
A. A third shift now, a new line when it is needed. Run the third shift until demand passes 1.8 million units, and have the new line ready by then.
B. A new line now. Start the line in 18 months, and run only normal shifts.
C. A third shift only. Never build the line. Any demand above 1.8 million is turned away, and its contribution of ₹150 a unit is lost.
The numbers
Exhibit 1: what an extra unit costs under each option
· Third shift · New lineFixed cost a year · ₹1.2 crore · ₹5.75 crore
Extra cost per unit · ₹45 · none
Capacity added · 0.6 million · 1.0 million
Cost per extra unit if fully used · ₹65 · ₹57.5
Cost per extra unit if 0.6 million are made · ₹65 · ₹95.8
The third shift costs ₹65 a unit when it is full, ₹20 of fixed cost and ₹45 of premium. The new line costs ₹57.5 a unit when full, which is cheaper, but ₹95.8 if only 0.6 million units are made, since the fixed cost of ₹5.75 crore is spread over fewer units. The new line becomes the cheaper option only when it is used for more than about 1.0 million extra units a year (₹4.55 crore of extra fixed cost divided by the ₹45 premium it saves). That is more than a third shift can supply.
Exhibit 2: the cost at different levels of demand
The table gives the yearly cost of the added capacity at several demand levels. It includes the lost contribution of ₹150 for any unit that cannot be made.
Demand · Third shift: cost · Third shift: lost sales · New line: cost · Cheaper1.4 million · ₹2.10 crore · none · ₹5.75 crore · Third shift
1.6 million · ₹3.00 crore · none · ₹5.75 crore · Third shift
1.8 million · ₹3.90 crore · none · ₹5.75 crore · Third shift
2.0 million · ₹3.90 crore · ₹3.00 crore · ₹5.75 crore · New line
2.2 million · ₹3.90 crore · ₹6.00 crore · ₹5.75 crore · New line
Up to 1.8 million units, the third shift is cheaper than the new line, by ₹1.85 crore at the top. Beyond that, a third shift cannot supply more, and every unit of demand turned away costs ₹150 of lost contribution. At 2.0 million, the shift plan costs ₹6.90 crore in all, including lost sales, against ₹5.75 crore for the new line.
Exhibit 3: the five-year plans
At 12 per cent growth, demand is 1.34, 1.50, 1.69, 1.89 and 2.12 million units in years 1 to 5. The yearly cost of each plan, including lost sales, in crore of rupees:
Year · Demand · A. Third shift, then a line · B. A new line now · C. A third shift only1 · 1.34 million · 1.85 · 5.75 · 1.85
2 · 1.50 million · 2.57 · 5.75 · 2.57
3 · 1.69 million · 3.39 · 5.75 · 3.39
4 · 1.89 million · 5.75 · 5.75 · 5.22
5 · 2.12 million · 5.75 · 5.75 · 8.63
Five-year total · · 19.3 · 28.7 · 21.7
Plan A, a third shift now and a new line when demand passes 1.8 million, costs ₹19.3 crore over five years, ₹9.4 crore less than building the line now. Plan C, a third shift for good, is ₹2.4 crore dearer than A, because it loses sales in years 4 and 5. A new line built early costs ₹5.75 crore in year 1 to supply 0.14 million extra units that a third shift could have supplied for ₹1.85 crore.
Exhibit 4: how much depends on the growth rate
Demand growth is a forecast. The table shows the five-year cost under 6, 12 and 18 per cent growth.
Demand growth · A. Third shift, then a line · B. A new line now · C. A third shift only6% a year · ₹11.3 crore · ₹28.7 crore · ₹11.3 crore
12% a year · ₹19.3 crore · ₹28.7 crore · ₹21.7 crore
18% a year · ₹32.8 crore · ₹38.8 crore · ₹41.8 crore
At 6 per cent growth, demand never reaches 1.8 million within five years, and plan A is the same as C: it never builds the line, and saves ₹17.5 crore against building one now. At 18 per cent, demand passes 1.8 million in year 3, and A builds the line then. It costs ₹6.0 crore less than building at once, and ₹9.0 crore less than a third shift alone. In all three cases, building a new line now is never the cheapest, and a third shift followed by a new line when needed is the cheapest or ties for it. The result is robust to the forecast.
Questions to consider
1. Why is the new line more expensive than a third shift at 1.4 million units and cheaper at 2.0 million?
2. What does the break-even volume of about 1.0 million extra units tell you, and why is it above what a third shift can supply?
3. Why does the best plan depend on the timing of the new line and not only on whether to build it?
4. How does the plan change if demand growth is 6 or 18 per cent, and what does that say about forecast risk?
5. Which costs and risks of a third shift are not in the model?
6. What would you recommend, and when would you place the order for the line?
Analysis
Step 1: fixed cost against variable cost
The two options are mirror images. A third shift has a low fixed cost, ₹1.2 crore, and a high cost per unit, ₹45 extra. A new line has a high fixed cost, ₹5.75 crore, and no extra cost per unit. The same pattern appeared in the make-or-buy decision in Case 94: the choice depends on volume, and the option with the high fixed cost needs a large volume to pay.
At 0.2 million extra units the third shift costs about ₹2.1 crore and the line ₹5.75 crore. At 0.6 million the third shift costs ₹3.9 crore. The new line becomes cheaper only if a third shift could supply a million extra units, and it cannot. A third shift is therefore the cheaper way to supply every unit it can supply, and the only question is what happens when it runs out.
Step 2: the cost of being short
The reason to build a line is not that it is cheaper per unit, but that it can make units that nothing else can. Beyond 1.8 million units, every unit of demand is either made on a new line or lost. At ₹150 of contribution per unit, turning away 0.3 million units costs ₹4.5 crore a year, which is nearly as much as the new line costs. A new line that makes 1.0 million units' worth of room is worth ₹15 crore of contribution a year if the demand is there, much more than its ₹5.75 crore cost.
It follows that the line pays once demand exceeds about 1.8 million plus a few hundred thousand units. By Exhibit 2, at 2.0 million units it already costs ₹1.15 crore less than the third shift plan. A line is a way to avoid losing sales, and its value depends on when and how far demand outruns the third shift.
Step 3: why timing matters
A new line costs ₹5.75 crore a year from the day it is installed, even if it is half empty. If it comes too early, the plant pays for capacity it does not need. In plan B, Cooltec pays ₹5.75 crore in year 1 to supply 0.14 million units that a third shift could supply for ₹1.85 crore. The cost of building early is ₹3.9 crore in year 1, ₹3.2 crore in year 2 and ₹2.4 crore in year 3, a total of ₹9.4 crore of unnecessary cost before the line is needed.
If it comes too late, sales are lost. In plan C, Cooltec loses ₹1.3 crore of contribution in year 4 and ₹4.7 crore in year 5. The right time is just before the third shift runs out. A line takes 18 months to build, so the decision has to be made well before that point. With 12 per cent growth, demand reaches 1.8 million early in year 4, and Neha must place the order for the line in the middle of year 2. This means she has to commit when demand is only 1.5 million, and rely on a forecast.
Step 4: the forecast risk
The sensitivity to growth shows how the plan copes with uncertainty. If growth is only 6 per cent, plan A never builds a line and costs ₹11.3 crore, less than half of B. If growth is 18 per cent, plan A builds in year 3 and costs ₹32.8 crore, ₹6.0 crore less than B. A staged approach has a very useful property: it is never the worst and is usually the best.
This is the value of an option. By starting with the cheap, flexible third shift, Cooltec buys the right to wait and see. It does not need to know what demand will be in year 5 to decide in year 1. It does need an early warning: a trigger that tells Neha when to place the order, such as "order the line when the forecast shows demand reaching 1.8 million units within 18 months", chosen to allow for the lead time.
Step 5: what the model leaves out
A third shift is not as simple as the cost of ₹45 a unit suggests.
Quality and safety. Night shifts have more errors and accidents. If defects rise more than assumed, the cost goes up, and the premium could be well above ₹45. If the premium exceeds ₹76 a unit, the new line is cheaper than a full third shift (₹4.55 crore of extra fixed cost over 0.6 million units).
Maintenance. A machine that runs three shifts has no time for planned maintenance, and breakdowns rise. Some plants keep a maintenance window every week.
People. Hiring and keeping a night workforce is hard in some places. Turnover can be high, and training costs rise.
Customers. Some customers audit factories and may be reluctant to accept products from a shift that is under-supervised.
A new line has its own risks: it may take longer than 18 months, cost more than ₹24 crore, or produce a poorer yield in its first year. It also brings benefits the model leaves out, such as newer technology with lower energy use and the ability to make new products.
Step 6: the recommendation
Neha might say: "Start the third shift now and prepare for a new line, but do not order it yet. On our forecast, a third shift followed by a new line when demand passes 1.8 million units costs ₹19.3 crore over five years, against ₹28.7 crore for building the line now and ₹21.7 crore for a third shift only. The line is the cheaper way to make units only above about 1.0 million extra units, so building it early wastes money. But it takes 18 months, so I will set a trigger: place the order when the forecast shows demand reaching 1.8 million units within 18 months, which at 12 per cent growth is the middle of year 2. If growth is 6 per cent we never need it, and if it is 18 per cent we order earlier. Track third-shift defects and downtime closely: if the extra cost per unit rises above ₹76, move the order forward."
What happened
This part of the case is an illustrative epilogue, not a real outcome.
Cooltec started a third shift on the compressor line, and the extra cost per unit came out at ₹52, above the ₹45 assumed, mostly from higher scrap in the first three months. Orders grew by 14 per cent in year 1 and 11 per cent in year 2. In the second quarter of year 2, with the forecast showing 1.8 million units within 18 months, Neha placed the order for the new line. It was commissioned 20 months later, two months behind plan, and the third shift covered the gap with some overtime on weekends. Neha reported that the five-year cost of extra capacity was about ₹20 crore, close to plan A, and that no sales had been lost.
Key takeaways
A third shift has a low fixed cost and a high cost per unit. A new line has a high fixed cost and a low cost per unit. The better choice depends on the volume.
A third shift cost ₹65 per extra unit when full and a new line ₹57.5 when full, but ₹95.8 if only 0.6 million units were made. The line is cheaper only above about 1.0 million extra units, more than a third shift can supply.
The reason to build a line is to avoid lost sales: every unit of demand above 1.8 million lost ₹150 of contribution.
A third shift now and a new line when needed cost ₹19.3 crore over five years against ₹28.7 crore for building at once and ₹21.7 crore for a third shift only.
The staged plan was the cheapest or nearly the cheapest at 6, 12 and 18 per cent growth, since it keeps the option to wait.
Set a trigger for ordering the line that allows for its lead time, and watch the real cost of the third shift: above ₹76 per unit the line becomes cheaper even when the shift is full.
Try this
Plan capacity for a business of your own. Set aside forty-five minutes.
1. Choose a plant, kitchen, warehouse or service team that is near its limit. Write current capacity, expected demand growth and the contribution per unit.
2. Define a short-term way to add capacity (extra hours or a temporary arrangement) with its fixed cost, its extra cost per unit and its maximum, and a long-term way (new equipment or space) with its cost, life, fixed cost, capacity and lead time.
3. Compute the cost of each at several demand levels, including lost contribution on demand that cannot be met, and the volume at which the long-term option becomes cheaper.
4. Build five-year plans: the short-term way only, the long-term way now and a staged plan. Compare their total cost.
5. Test demand growth at half and one and a half times your forecast.
6. Write a five-sentence recommendation: the plan, the numbers, the trigger for the long-term investment, the lead time you must allow and the cost or risk of the short-term option that would change your mind.
A good result is a cost per extra unit for each option, a cost table by demand, a five-year comparison of three plans, a growth sensitivity test and a trigger for ordering. Case 97 looks at how a plant keeps its machines running: fixing them when they fail or servicing them before they do.