Case 97: Maintain before it breaks, or fix it when it fails?
A rolling mill compares run-to-failure, calendar and sensor-based maintenance. Compare breakdowns, downtime and cost, and the best number of planned stops.
A machine that stops without warning is a small disaster. The production line behind it waits, orders slip and the maintenance team scrambles to find the fault and the part. A machine that is serviced on a schedule stops too, but on the plant's terms: at a quiet hour, with the parts ready and the people on hand. The difference is large. Yet servicing is not free. Every planned stop takes the machine out of production and costs labour and parts, and servicing too often wastes money on machines that were working perfectly well. So the question is not whether to maintain, but how much. In this case you play the head of maintenance at a steel rolling mill whose most important machine has been failing too often. You will practise computing the cost of a breakdown and the cost of a planned stop, finding the number of stops a year that minimises the total, seeing how the answer changes with the price of downtime, and judging whether sensors that tell you when a machine needs attention are worth their cost.
This is a composite case. Ironwave, its people and its figures are invented for teaching, built on patterns common among process plants and mills. No real company is described, and no number here should be quoted as a fact about any real firm.
The decision
Prakash Rane, head of maintenance at Ironwave, a steel rolling mill, is called to the manager's office after the fourth breakdown of the year on the main rolling stand. Each one stopped the mill for most of a day. The works manager wants to know why a machine that costs so much keeps failing, and what to do about it. At present Ironwave mostly fixes the stand when it breaks. Prakash has data on breakdowns and costs, and three alternatives to compare.
Background
What a breakdown costs. When the stand fails, the mill stops for about 14 hours while the fault is found and fixed. Each hour of stoppage costs about ₹3 lakh in lost contribution, because the mill's output is sold at a margin and the contract deadlines are tight. The repair itself costs about ₹8 lakh in parts and labour. So one breakdown costs about 14 × ₹3 lakh + ₹8 lakh = ₹50 lakh.
What a planned stop costs. A planned maintenance stop takes about 8 hours. It is scheduled at a quiet time, such as a weekend or a shift with a thin order book, when the lost margin is only about ₹0.8 lakh an hour. Parts and labour cost another ₹9 lakh. A planned stop therefore costs about 8 × ₹0.8 lakh + ₹9 lakh = ₹15.4 lakh, less than a third of a breakdown.
How maintenance reduces breakdowns. With no planned maintenance, the stand fails about 4 times a year. Prakash's records suggest that each planned stop in the year reduces the failure rate by about 36 per cent, so that with n stops a year the expected number of breakdowns is 4 × e^(−0.45 × n). The first stops remove the most failures, and later ones remove fewer.
Four options.
A. Run to failure. No planned stops. Fix the stand when it breaks.
B. Calendar maintenance (the plan on the table). Two planned stops a year, at fixed dates.
C. A better calendar. The number of stops that minimises total cost.
D. Condition-based maintenance. Fit sensors that measure vibration and temperature and alert the team when the stand needs attention. The sensors and the analysis service cost about ₹12 lakh a year. Planned stops are shorter, about 6 hours, and cheaper at ₹11.8 lakh each, because the team knows what to fix. Because the work is better timed, each stop is 40 per cent more effective at preventing breakdowns than a calendar stop.
The numbers
Exhibit 1: the cost at different numbers of planned stops
All figures are in lakh of rupees a year.
Planned stops a year · Expected breakdowns · Cost of planned stops · Cost of breakdowns · Total cost0 (run to failure) · 4.0 · none · ₹200.0 · ₹200.0
1 · 2.5 · ₹15.4 · ₹127.5 · ₹142.9
2 (calendar plan) · 1.6 · ₹30.8 · ₹81.3 · ₹112.1
3 · 1.0 · ₹46.2 · ₹51.8 · ₹98.0
4 · 0.7 · ₹61.6 · ₹33.1 · ₹94.7
5 · 0.4 · ₹77.0 · ₹21.1 · ₹98.1
6 · 0.3 · ₹92.4 · ₹13.4 · ₹105.8
The total falls from ₹200.0 lakh with no maintenance to ₹94.7 lakh with four stops a year, a saving of 53 per cent, and then rises again. At five and six stops, the extra planned stops cost more than the breakdowns they prevent. The best number of stops is four: the fourth stop adds ₹15.4 lakh of cost and removes about 0.4 breakdowns, worth ₹18.8 lakh. The fifth stop costs ₹15.4 lakh and saves only ₹12.0 lakh.
Exhibit 2: the shape of the curve
The curve is steep at the left and flat at the bottom. Moving from no maintenance to one stop saves ₹57.1 lakh. From one stop to two saves ₹30.8 lakh, and from two to three ₹14.1 lakh. After four stops, extra effort is wasted. A plant that has no planned maintenance gains the most by starting. A plant that already has a good programme gains little by adding to it.
The flatness around the optimum is useful. At three stops the cost is ₹98.0 lakh, only 3.5 per cent above the best, and at five, ₹98.1 lakh. The exact number of stops matters less than being in the range of three to five. The current plan of two stops, ₹112.1 lakh, is 18 per cent above the best.
The formula for the best number of stops is n = ln(b × k × F ÷ c) ÷ k, where b is the failures a year with no maintenance (4), k the effectiveness (0.45), F the cost of a failure (₹50 lakh) and c the cost of a planned stop (₹15.4 lakh). It gives 3.9 stops.
Exhibit 3: how much depends on the cost of downtime
The cost of an hour of downtime, ₹3 lakh, is the number that drives everything. It depends on the order book: in a slack market an hour of downtime costs less, and in a tight one more.
Cost of an hour of downtime · Run to failure · Two stops · Three stops · Four stops · Five stops · Best number of stops₹1 lakh · ₹88.0 · ₹66.6 · ₹69.0 · ₹76.1 · ₹86.3 · 2
₹3 lakh (base) · ₹200.0 · ₹112.1 · ₹98.0 · ₹94.7 · ₹98.1 · 4
₹6 lakh · ₹368.0 · ₹180.4 · ₹141.6 · ₹122.4 · ₹115.8 · 5
When downtime is cheap, ₹1 lakh an hour, two stops are enough, and running to failure costs ₹88 lakh, 32 per cent more than the best plan. When downtime is dear, ₹6 lakh, five stops are best, and running to failure costs ₹368 lakh, more than three times the best plan. The more a stoppage costs, the more maintenance is worth.
Exhibit 4: are sensors worth it?
Option D uses sensors to time the work. It has a fixed cost of ₹12 lakh a year, shorter and cheaper stops, and a claimed 40 per cent gain in effectiveness. With three stops a year, the cost is:
Planned stops: 3 × ₹11.8 lakh = ₹35.4 lakh.
Breakdowns: 4 × e^(−0.45 × 3 × 1.4) = 0.6 a year, costing ₹30.2 lakh.
Sensors and service: ₹12.0 lakh.
Total: ₹77.6 lakh, 18 per cent below the best calendar plan (₹94.7 lakh) and 61 per cent below running to failure.
The claim of 40 per cent greater effectiveness is the weak point. The table shows the cost of option D at other values.
How much more effective each stop is · Breakdowns a year · Total cost of option DNone (1.0 times) · 1.04 · ₹99.3 lakh
20% more (1.2 times) · 0.79 · ₹87.0 lakh
40% more (1.4 times, base) · 0.60 · ₹77.6 lakh
60% more (1.6 times) · 0.46 · ₹70.5 lakh
Sensors pay once they make each stop at least about 7 per cent more effective: below that, option D costs more than the best calendar plan. At 20 per cent, the saving is ₹7.7 lakh a year, at 40 per cent ₹17.1 lakh. The sensors' value is that they do not only prevent breakdowns: they make the stops shorter and cheaper, because the team arrives knowing what to fix. That part of the gain does not depend on effectiveness.
Questions to consider
1. Why does a planned stop cost so much less than a breakdown, and what does that say about when to maintain?
2. Why does the total cost have a lowest point, and what does the bottom of the curve look like?
3. How does the cost of downtime change the best amount of maintenance?
4. What would make sensor-based maintenance worth the cost, and what could go wrong with it?
5. Besides cost, what else matters in a mill's decision: safety, quality and the ability to meet contracts?
6. What would you recommend, and how would you check that it works?
Analysis
Step 1: the asymmetry between planned and unplanned
The central fact is that a stoppage at the wrong time costs far more than one at the right time. A breakdown costs ₹50 lakh: 14 hours at ₹3 lakh an hour plus the repair. A planned stop costs ₹15.4 lakh: 8 hours at ₹0.8 lakh an hour plus parts. The planned stop is cheaper per hour, because it is placed where it hurts least, and shorter, because the team has the parts and the plan. It is also cheaper in less visible ways: orders are not missed, rush freight is not needed and no one works through the night in a panic.
This asymmetry is why maintenance pays. If planned and unplanned stops cost the same, there would be no point in scheduling them. The gap of about ₹35 lakh per event is the value of choosing when a stop happens. The question is how many stops to buy it with.
Step 2: the curve of diminishing returns
Each additional planned stop reduces the expected number of breakdowns by the same percentage, 36 per cent, so each removes fewer in number. The first stop takes the failure rate from 4.0 to 2.5, removing about 1.5 breakdowns, worth ₹72.5 lakh. The fourth takes it from 1.0 to 0.7, removing about 0.4, worth ₹18.8 lakh, a little more than its cost of ₹15.4 lakh. The fifth removes 0.24, worth ₹12.0 lakh, less than its cost. This is the basis for the best of four stops.
The same logic applies to any activity that reduces a risk: each extra unit of effort buys less. The point to stop is where the extra cost equals the extra benefit. It is a lesson that applies beyond machines, to inspection, testing and safety.
Step 3: why the best number moves
The best number of stops responds to the price of downtime and to the cost of a stop. When downtime costs ₹1 lakh an hour, a breakdown costs ₹22 lakh, not far above the ₹15.4 lakh of a planned stop, and two stops are enough. When it costs ₹6 lakh an hour, a breakdown costs ₹92 lakh, and five stops are justified.
This suggests that maintenance should follow the commercial position of the mill. When the order book is full and margins are high, as in a boom, every hour counts, and the plant should maintain more. When it is slack, the plant can accept more risk. Many plants do the opposite: they cut maintenance in a downturn to save money, and then suffer breakdowns when demand returns.
Step 4: what sensors add
Sensors change the maintenance process from calendar-based to condition-based. A calendar plan services the machine at fixed intervals, whether or not it needs it. Some stops are wasted on a machine in good condition, and others come too late for a machine that is deteriorating. A sensor measures what is happening, such as vibration that rises as a bearing wears, and tells the team when to act.
The benefits in the model are three: stops that are better timed, shorter stops and fewer stops (three instead of four). The costs are the ₹12 lakh a year and the work of setting up and interpreting the data. The risks are real. Sensors give false alarms, and a team that ignores them loses the benefit. A model of failure that has not been checked against the plant's own history may be wrong. And a sensor does not fix anything: it needs a team that acts on what it finds.
A sensible approach is to try sensors on the one or two machines where downtime is most costly, compare the results with the calendar plan for a year and extend them if the breakdowns and the cost of stops fall as expected.
Step 4: what else maintenance protects
The model counts the cost of lost margin and repair. Other costs exist and make the case for maintenance stronger.
Safety. A bearing or gearbox that fails violently can injure people. A planned inspection is the best defence.
Quality. A worn machine produces off-specification steel, and scrap and rework costs rise before it fails.
Customers. A missed delivery to a major customer can lose a contract.
Equipment life. A machine that is looked after lasts longer, and delays an expensive replacement.
Secondary damage. A failure of one part often damages others. Replacing a ₹2 lakh bearing on schedule avoids a ₹15 lakh repair of the shaft it ruins.
These costs make breakdowns more expensive than the model shows, and push the best number of stops higher.
Step 5: how to check it works
Prakash should treat the plan as a hypothesis and track the results.
Breakdowns and hours lost, compared with the plan's forecast.
Cost per planned stop and the share of stops that found a real fault. If most stops find nothing, they are too frequent. If they find serious faults, they may be too rare.
The cause of each breakdown, to see whether the stops are addressing the right parts.
Spare parts. Planned stops depend on the parts being at hand.
After a year, he can compare the actual cost with the ₹94.7 lakh forecast, adjust the number of stops and decide whether to extend the sensors.
Step 6: the recommendation
Prakash might say: "Move from two planned stops a year to four, and trial sensors on the main stand. On our figures, running to failure costs about ₹200 lakh a year, two stops cost ₹112 lakh and four stops cost ₹95 lakh, the lowest of the calendar plans. A breakdown costs ₹50 lakh and a planned stop ₹15 lakh, so each stop pays while it prevents more than about 0.3 breakdowns (₹15.4 lakh divided by ₹50 lakh). Sensors could cut the cost to ₹78 lakh if they make stops 40 per cent more effective, and are worth it if the gain is more than about 7 per cent. Schedule the stops in the quietest weeks, keep the key parts in stock and record every fault found. If the cost of downtime rises above ₹3 lakh an hour, increase the stops to five."
What happened
This part of the case is an illustrative epilogue, not a real outcome.
Ironwave moved to four planned stops a year and fitted vibration sensors to the main stand. In the first year there was one breakdown, lasting 9 hours, against four the year before. The sensors flagged a bearing that was running hot six weeks before it would have failed, and the team replaced it during a planned stop. Total maintenance, sensor and breakdown cost was about ₹94 lakh, in line with the forecast and less than half of the ₹200 lakh of the year before. Prakash noted that two of the four planned stops found nothing significant, and cut the following year's plan to three stops with condition checks between them.
Key takeaways
A breakdown cost ₹50 lakh and a planned stop ₹15.4 lakh, because planned stops happen in quiet hours with parts ready.
Running to failure cost ₹200 lakh a year. Two stops cost ₹112.1 lakh. Four stops, the best calendar plan, cost ₹94.7 lakh, a saving of 53 per cent.
Each extra stop removes fewer breakdowns, and beyond four the stops cost more than the breakdowns they prevent.
The best number of stops rises with the cost of downtime: two stops at ₹1 lakh an hour, four at ₹3 lakh and five at ₹6 lakh.
Sensor-based maintenance cost ₹77.6 lakh if stops were 40 per cent more effective, and paid for itself if they were at least about 7 per cent more effective.
Track breakdowns, hours lost, cost per stop and what each stop finds, and adjust. Do not cut maintenance in a slump and then meet demand with unreliable machines.
Try this
Plan the maintenance of a machine or system of your own. Set aside forty-five minutes.
1. Choose a machine, vehicle or system that sometimes fails. Write the cost of an hour of unplanned downtime, the hours lost in a failure and the repair cost.
2. Write the cost of a planned stop, with the hours it takes, the cost of an hour of planned downtime and the parts and labour.
3. Estimate the failures a year with no maintenance and how much each planned stop reduces them. Compute the total cost for 0 to 6 planned stops, and find the best number.
4. Test the best number at half and double the cost of downtime.
5. Estimate what a monitoring system would cost and how much it would improve the effectiveness and cost of stops, and compute whether it pays.
6. Write a five-sentence recommendation: the number of stops, the numbers, the cost of downtime you assumed, whether you would add monitoring and how you would check results.
A good result is a cost table for 0 to 6 stops, a best number, a sensitivity test on the cost of downtime, a test of sensors and a plan for tracking. Case 98 looks at a different threat to a factory's profit: a sudden rise in the price of its main raw material.
Tags: Case study Manufacturing Maintenance Downtime Reliability